Monday, 26 January 2015

BMSTC Refurbishment update

Work is cracking on with our refurbishment!  Upstairs should be complete by the end of this week with carpets being laid as I type!


The decorators have started to move downstairs and are doing their very best to work around us so we can continue to operate.  The main physio gym ceiling was painted over the weekend, and physio rooms 1 & 2 will be stripped out this week including the WC in between them ready for decoration and first fix next week. 


The decorators will be working in the shop and dieticians room off reception this week and hope to start painting the gym and physio 1 & 2 over the next couple of weeks. 


Apologies for all of the disturbance, dust and noise!   We will keep you informed as work progresses, and will to our upmost do operate the best service we can whilst the work is undertaken.


Best wishes


Pip