Tuesday, 24 March 2015

Refurb update 6

The coffee point in reception will be installed today, 24th March.


The inside of the chamber will be painted this Thursday and Friday, 26th and 27th March.  Oxygen therapy has been cancelled for these two days and we hope the paint smell will have subsided sufficiently to run the Saturday 28th March sessions.


The wet room off the gym and WC next to the counselling room have been stripped out and will be installed and ready to use by the middle of next week, 1st April.  The 2 WC's by the kitchen will then be stripped out and replaced, hopefully ready for use by 10th April.


The flooring in the main reception area, office and oxygen room will be the last major work to take place.  It is likely that we will need to close the Centre whilst this work takes place.  We will give you as much advance warning as possible.  We are delighted that this will be the only time during the refurbishment that we have had to close the Centre, and we have done our very best to reduce cancellations to therapies.


Once again thanks for your patience and understanding with the chaos, disruption and noise.  The end is finally in sight!